Week 12: Insulation done

Mick helped drywall the items in the attic that needed spray foam insulation.  John from A&J Windows installed the back sliding door which looks awesome!  George finished and had the insulation inspected by the end of the week.

Week 11: Getting ready for drywall (and trim?)

We had a bunch of trim samples in the house this week, and Jess and Sharon selected a pretty clean, basic option that will work well with their decor. The drywall was delivered throughout the house, so we are raring to go!

Week 10: Progress

Stone complete? Check!  Tub installed? Check!  Tech and central vac roughed-in? Check!!!

Week 9: Windows and stone

The windows were installed (luckily I transferred some math skills to the stucco installed and everything worked out (we usually do stucco AFTER windows!)) and Thom made great progress on the stone in the front.

Week 8: Moving Along

Dave and Jess decided they'd like stone on the front... and lickity split, we had the stone stripped and disposed of.  The backframing progressed inside and the stucco is really moving!

Week 7: HVAC Continues, Stucco Starts

The HVAC work continues in the basement  while we have managed to strip the old exterior cladding and get the new stucco system started.  This will be a huge improvement in quality on the outside.

Week 6: HVAC and Plumbing R/I begin

The HVAC and plumbing rough-ins started last week.  For HVAC, we're reconnecting/moving all of the existing systems to work with the current wide open plan.  We'll have to get creative with the duct work and plumbing that has to run under the steel beams now - always an issue with open-concept living.