Stone complete? Check!  Tub installed? Check!  Tech and central vac roughed-in? Check!!!




Comments

Popular posts from this blog

Week 20: Trim carpentry progress

Trim carpentry continues to progress and impress.  I like the black hinges and handles Sharon has chosen.  Now that the doors are hung, the upstairs is really taking shape.

Week 21: Basement flooring and front door

With most of the big deliveries in the house, we had John from A&J Windows install the front door so we could trim it out properly on the inside. Jampa began floor leveling applications in the basement.  We are doing our best working with the existing slab, but it's not easy finding a happy balance of "what is level" sometimes.

Week 11: Getting ready for drywall (and trim?)

We had a bunch of trim samples in the house this week, and Jess and Sharon selected a pretty clean, basic option that will work well with their decor. The drywall was delivered throughout the house, so we are raring to go!