The HVAC and plumbing rough-ins started last week. For HVAC, we're reconnecting/moving all of the existing systems to work with the current wide open plan. We'll have to get creative with the duct work and plumbing that has to run under the steel beams now - always an issue with open-concept living.
With most of the big deliveries in the house, we had John from A&J Windows install the front door so we could trim it out properly on the inside. Jampa began floor leveling applications in the basement. We are doing our best working with the existing slab, but it's not easy finding a happy balance of "what is level" sometimes.