Week 20: Trim carpentry progress

Trim carpentry continues to progress and impress.  I like the black hinges and handles Sharon has chosen.  Now that the doors are hung, the upstairs is really taking shape.

Week 19: Trim carpentry starts

Jampa has finished the floors and 1 and 2 (basement still to come) and has completed the fireplace framing and begun the trim carpentry.  It was a big week inside at 36 Walford!

Week 18: Meanwhile, outside

While the floors continued inside, George was around to do the prefinished metal roof and some other details.  Landscaping  on the front (only) starts soon!

Week 17: Flooring... check!

Jampa officially took residence in the house... starting with floors, he will be in and out for the better part of  the next 8-9 weeks!

Week 16: Tile Installation

Fred ("you pick 'em, I stick 'em") was in all week doing the tile work.  In the shower below the designer was going for more of a wood look on the back wall to match the hardwood floors.... 

Week 15: Tile Prep

Freddy was in, prepping the floors for tile and working with Kevin to coordinate the floor warming for the master ensuite.  Tile should be done and floors started next week!

Week 14: Taping Done!

Despite a lot of humidity, the drywall tapers managed to finish this week.  The house looks great!